Cement & Concrete Calculator

सिमेन्ट तथा कंक्रिट क्याल्कुलेटर

Estimate cement bags, sand, aggregate, water and material cost for a concrete pour, with wastage and editable local prices.

Estimate cement bags, sand, aggregate and water for a slab, footing or column. Choose a nominal mix, allow for wastage, and edit the local prices to match your supplier.

Land & ConstructionFree · No sign-up
Allowance for spillage, over-excavation and breakage.
1.54 is the usual site assumption. Change only if you have a reason.
Local material prices (editable)

Defaults are indicative Kathmandu Valley rates for October 2026. Enter the rate your supplier quotes — delivery, VAT and distance change the price.

Cement required—
Mix
—
Wet volume
—
Dry volume
—
Cement mass
—
Cement bags
—
Sand
—
Coarse aggregate
—
Water (approx.)
—
Material cost
—
Cost per m³
—

Cost breakdown

MaterialQuantityRateAmount
    Free to use · Works in your browserQuestions & sources

    About the cement and concrete calculator

    This calculator turns a slab, footing or column volume into the cement, sand, aggregate and water you need to buy. Enter the length, width and thickness — mixing feet with inches is fine — choose a nominal mix such as M20 (1 : 1.5 : 3), set a wastage allowance, and the result gives cement bags, sand and aggregate in cubic feet, water in litres and an editable material cost. It uses the standard site method, so it is a purchase estimate rather than a structural design.

    How the quantities are worked out

    The wet volume is length × width × thickness in cubic metres. Dry materials bulk up when mixed, so the wet volume is multiplied by a dry-volume factor of 1.54. Each material then takes its share of the mix: for M20, cement is 1 part, sand 1.5 parts and aggregate 3 parts out of 5.5. Cement volume is converted to mass at 1,440 kg per cubic metre, then divided into 50 kg bags and rounded up, because you cannot buy part of a bag. Sand and aggregate are converted to cubic feet, the unit most Nepali suppliers quote.

    Nominal mixes and when they stop being enough

    M7.5 (1 : 4 : 8), M10 (1 : 3 : 6), M15 (1 : 2 : 4) and M20 (1 : 1.5 : 3) are nominal mixes — fixed volume ratios used on small and medium buildings. They are convenient but do not guarantee strength, because the actual cement content, water and aggregate grading vary. M25 and above should be a tested design mix, and anything structural should follow the drawings and the engineer's specification. The calculator flags this when you pick M25, but the same caution applies to any mix on a critical element.

    Wastage, water and real sites

    A 5% wastage allowance is a sensible default for bag work and site mixing; increase it for small pours, rough ground or a site where bags are opened and left standing. Water is shown at a water–cement ratio of 0.5, which is workable for many mixes but too wet for some exposures and too dry for others. More water makes concrete easier to place and weaker when it sets, so treat the litres as a starting point and follow the mix design or the engineer's instruction.

    Local prices

    Material prices move with location, transport and the season. The defaults — Rs 730 per 50 kg bag of cement, Rs 115 per cft of sand and Rs 120 per cft of aggregate — are indicative Kathmandu Valley rates for October 2026, and every one of them is editable. Enter the rates your supplier has quoted. The cost shown is materials only: it excludes labour, steel reinforcement, formwork, pumping, transport and VAT, all of which can be a large part of the final bill.

    Units and accuracy

    Length and width can be in feet or metres; thickness can be in inches, millimetres, centimetres, metres or feet. That covers the common Nepali site mix of a room measured in feet and a slab measured in inches. The result is rounded for display, but the underlying calculation keeps full precision, so a small change in thickness does not produce a misleading jump. For a large or structural pour, order against the engineer's bar-bending schedule and mix design, not this estimate alone.

    Frequently asked questions

    How many cement bags are in one cubic metre of M20 concrete?
    With the usual 1.54 dry-volume factor and 50 kg bags, one cubic metre of M20 (1 : 1.5 : 3) needs about 403 kg of cement, or 9 bags, before wastage. With 5% wastage it is still 9 bags after rounding up; a larger pour or a higher wastage allowance can push the count to the next bag.
    What is the 1.54 dry-volume factor?
    It is a site approximation for the bulking of loose sand and aggregate and the voids between particles. The wet volume of concrete is multiplied by 1.54 to estimate the dry material volume. It is not a precise physical constant; a design mix uses measured aggregate properties instead.
    Can I use this calculator for an M25 mix?
    You can use it as a rough check, but M25 and above should be a tested design mix. Nominal ratios do not control the water–cement ratio or aggregate grading closely enough for higher-strength structural work. Follow the engineer’s mix design for the actual pour.
    How much wastage should I allow?
    About 5% is a common default for bag work and site mixing. Use more for small pours, rough ground, remote sites or bagged material that will sit around. The wastage is already included in the bag count, sand and aggregate shown.
    Does the cost include labour and steel?
    No. The cost covers cement, sand and aggregate only. Labour, steel reinforcement, formwork, pumping, transport and VAT are separate and can be a large share of the total. Add them from your own quotes.
    Why does the cement bag count jump?
    Bags are sold whole, so the calculator rounds up. A small increase in volume or wastage can cross a bag boundary. The cement mass in kilograms is shown too, so you can see how close the pour is to the next bag.